|
Friday,
October 8, 1999 Published at 15:55 GMT 16:55 UK
Paddington:The crash report in full

The crash was caused by a train passing
through a red signal

The Health and Safety Executive
has revealed its interim findings about the London rail disaster.
Train accident at Ladbroke
Grove Junction, 5 October 1999
First HSE interim report,
8 October 1999
1. This is the
first interim response to HSC's request for an investigation and report
under section 14(2)(a) of the Health and Safety at Work etc Act 1974.
It will also be made available to Lord Cullen and Professor Uff for the
purposes of the two relevant inquiries and to Sir David Davies who is
preparing advice for the Deputy Prime Minister.
The accident
2. At 8.11am on 5 October
two trains collided 2 miles outside Paddington station, at Ladbroke Grove
Junction. One was a Great Western High Speed Train (HST) running from
Cheltenham Spa to Paddington, the other a Thames Train 3-car diesel unit
going from Paddington to Bedwyn, in Wiltshire. 30 people are already confirmed
as dead and many more are unaccounted for. There are also 160 injured,
some critically, because of a rapid outbreak of fire in some of the HST
carriages.
The investigation
3. HSE's Railway Inspectorate
(RI) is investigating the cause of the accident with the aim of answering
three main questions:
- why did the accident happen?
RI is looking not just at the immediate and technical issues but also
at the root causes;
- what remedial action needs
to be taken to prevent a further accident? RI can insist on immediate
or longer-term remedial action as appropriate, using wide-ranging powers
under the Health and Safety at Work etc Act 1974 (HSWA);
- does what was done (or undone)
merit further enforcement action (including prosecution)? A prosecution
could be taken under HSWA or, if there was evidence of gross negligence,
the Crown Prosecution Service could be asked to consider a charge of
manslaughter, which is outside the scope of the charges that HSE is
empowered to deal with.
4. The final report will
take some time to complete but, as significant findings come to light,
RI will make them public and will also take action where this is appropriate.
This interim report sets out the initial findings from the first three
days' worth of work.
5. Key points
- The immediate cause of the
accident appears to be that the Thames Train passed a red signal (a
"signal at danger") some 700m before the collision point. The reasons
why the train passed the red light are likely to be complex. RI will
be looking at the underlying causes as well as any more obvious ones.
Our belief is that it is a systems failure and that any action or omission
on the part of the driver was only one factor.
- Analysis of data tapes suggest
that the signalling equipment is unlikely to have been at fault. This
cannot be fully confirmed until all the testing of the trackside equipment
relevant to signal SN109 has been completed.
- Early evidence suggests that
the accident would have been prevented by installation and correct operation
of a Train Protection Warning System (TPWS). Moreover the signal in
question is one which is required to be fitted with TPWS by 31 December
2003 by virtue of the recent Railway Safety Regulations 1999.
- As part of a pilot scheme,
Automatic Train Protection (ATP) equipment was fitted to the Great Western
train. However, experience has shown the ATP to suffer from reliability
problems and the equipment was switched off because it was not operational.
However, on the evidence gained so far, this was unlikely to have had
a bearing on the accident. Because of other investigations it has not
yet been possible to establish if the ATP in the rear cab was working.
- Despite substantial damage
to the leading vehicle of the Great Western train, we know that the
driver's Automatic Warning System device was not switched off. However,
we cannot tell whether it was operational at this stage, neither is
the result likely to have any bearing on the accident
Layout of the accident site
6. A greatly simplified
diagram at Appendix 1 (for illustrative purposes only) shows the layout
of the lines where the accident happened, which is also described in the
following paragraphs. There are also some photographs showing the crash
site. (The appendix and photographs referred to above will be made available
shortly)
7. To the west of Ladbroke
Grove Junction there are four running lines:
- the Up and Down Main lines
and
- the Up and Down Relief lines.
The "Up" direction of travel is towards Paddington.
8. To the east of Ladbroke
Grove Junction there are six bi-directional running lines identified as
Lines 1 to 6. At the junction there are connections between the various
lines.
9. The Up Main line becomes
Line 2. There is a high-speed connection from the Up Main Line to Line
3 just to the east of the Up Main line signal SN120 for trains travelling
towards Paddington. Further to the east there is a crossover between Line
3 and the Down Relief line. Further east still there is another crossover
from Line 3 to the Up Main line and another crossover between the Up and
Down Main lines which allows trains travelling towards Reading to cross
from Line 3 to the Down Main line. Line 3 does not extend to the west
of Ladbroke Grove Junction.
Signal SN109
10. Access from Line 3
to either the Down Main or Down Relief lines, for trains travelling towards
Reading, is controlled by signal SN109. The signal is located on a gantry
which spans all six of the lines and which also carries signals for each
of the other lines. The distance between signal SN120 on the Up Main line
and Signal SN109 on Line 3 is some 700m.
The signalling system
11. The signalling at
Paddington is controlled by a Solid State Interlocking (SSI) system located
at the Slough Control Centre. The system also includes a computer-driven
Automatic Route Setting (ARS) facility. ARS requests the SSI to set routes
for trains in accordance with a pre-loaded timetable, instead of the signaller
doing it manually.
On the morning of the collision
the ARS was in use and the signaller at the Control Centre was visually
monitoring the progress of trains, using VDU displays on the control desk.
The routes set for the two trains
12. The 6.03 Cheltenham
to Paddington train (train 1A09) was following an earlier train along
the Up Main line towards Paddington. After the signals had turned back
to red behind the previous train, they progressively turned back through
yellow to double yellow and then green as the train proceeded - which
is normal. Therefore, 1A09 was travelling on green signals a safe distance
behind the previous train.
13. The ARS had set a
route for the 08.06 Paddington to Bedwyn train (train 1K20) up to Signal
SN109 on Line 3. The train on leaving Paddington Station had travelled
on Line 4 and crossed on to Line 3 on the approach to SN109.
Signalling systems: RI's findings
so far
14. On the morning of
Tuesday 5 October Mr Alan Cooksey, Deputy Chief Inspector of Railways,
went directly to the control centre at Slough where he confirmed with
the signallers what they had observed from the signalling displays. He
also oversaw the removal of the data recording tape from the SSI and the
initial analysis of the information it contained.
Analysis of the SSI data
15. There are data tape
records of:
- each instruction given to
the SSI from the ARS or signaller
- the instructions given by
the SSI to the signals and points
- the response from the signals
and points
- the progress of the trains
detected by the track circuits.
16. While a high level
of confidence can be gained from the analysis of the SSI data tapes, we
cannot absolutely confirm that all of the signal equipment at the site
did function in accordance with the instructions issued by the SSI until
each piece of equipment from the site has been tested.
That work is in progress at the
moment. In particular, we must be absolutely certain to ensure that although
signal SN109 was required to be showing a stop (red) aspect and reported
back to the SSI as doing so, that there is no possibility, however unlikely,
that it was showing any other aspect.
What follows is the most likely
sequence of events, based on present knowledge. RI's interpretation has
now been confirmed by an additional independent report from W S Atkins.
17. The signaller who
had been observing the progress of the trains on the VDU realised that
train 1K20 had passed Signal SN109 and was heading towards the Up Main
Line on which train 1A09 was approaching. He immediately changed signal
SN120 on the Up Main Line to Danger.
However, by that time train 1A09
must have been very close to the signal and travelling at speed (which
needs to be confirmed when analysis of the data recorder from the rear
cab is to hand) and the collision occurred almost simultaneously.
18. Examination of the
SSI data tape confirms that the route for train 1A09 had been requested
by the ARS, the instructions were processed by the SSI, and the commands
issued to the computer modules which control the signals and points for
a route from the Up Main Line to Line 2 and Paddington Station.
The signal aspects displayed
for 1A09 and its progress through the occupation and then clearing of
the relevant track circuits were also confirmed from the data tapes.
19. The data tapes also
confirm the ARS requesting the route up to Signal SN109, which was showing
a red aspect, for train 1K20. Subject to the further tests outlined above,
the likelihood is that train 1K20 therefore passed a red light. The data
tapes show the progressive occupation of track circuits as train 1K20
passed signal SN109 and travelled some 700m into the path of train 1A09.
The other signals on the SN109
gantry
20. At the time train
1K20 approached Signal SN109 it appears that no other routes had been
set which would have resulted in the other signals on the gantry showing
any aspects other than red.
Other issues
21. HSE has deployed two
fire experts from the Health and Safety Laboratory to investigate the
nature of the fire. They have made a survey of the fire damage where access
has been possible to do this:
- A major fire appears to have
occurred in Coach H of the HST but it has not yet been possible to investigate
the nature and extent of this fire.
- Diesel fuel has been spilled
over a wide area of the track and trackside. The sources of this fuel
have been identified as the three fuel tanks from the Thames train and
from the forward tanks of the HST. As a result of this spill, fires
occurred in the central Thames train carriage and on the south side
of Coaches C to H of the HST.
22. On this basis of what
we know so far about the speed of train 1K20, the accident was preventable
by the Train Protection Warning System (TPWS).
23. We have also made
a videotaped reconstruction of 1K20's approach to signal SN109, which
shows that there are issues relating to signal siting which need further
investigation.
24. Further lines of enquiry
for RI's investigation will include:
- checks on equipment, including
the final checks of the signalling equipment
- further forensic work on the
site, before it is cleared
- scrutiny and analysis of driver
training and asset maintenance records.
|