Investigations into the Potters Bar rail crash are
focusing on why there were missing nuts and bolts on the points system.
The points, at which the train derailed, killing seven and injuring
about 40, are being cut out and sent to the Health and Safety Executive's
laboratory for a forensic examination.
A set of nuts at the points have already been removed and are being
inspected by the HSE.
Experts say loose nuts
caused a "stretcher bar" at the points to fracture
|
The points, the mechanisms which divert trains onto different tracks,
contain three "stretcher bars" which keep the tracks in place as the train
passes over them.
Each of these stretcher bars is held in turn by four anti-vibration
nuts. At Potters Bar it is believed at least two sets of nuts were missing
- one on each of the second two stretcher bars.
This meant they were not fully bolted on and did not share the pressure
as the train passed. The subsequent pressure on the first stretcher
bar caused it to fracture, sending the fourth carriage off the rails.
'Vandalism' theory
But the question remains as to why the points were not functioning
properly.
They were checked just the day before the crash, according to Jarvis,
the company responsible for maintaining the track at the scene.
|
|
 |
Potters
Bar crash
Seven people died
Two are still critically injured
Investigation teams are combing the scene
|
 |
Transport Secretary Stephen Byers told the Commons
on Monday Railtrack had subsequently inspected 800 sets of points across
the country and found no similar defects.
At the weekend there was speculation that vandals
were to blame.
But this theory became increasingly unlikely
as it emerged that specialist equipment would have been needed to remove
the nuts.
It would also have to have been done in full
view of the station, which has CCTV, on a live track.
More likely, experts are now concluding, was
that poor maintenance played a role.
Rail expert Richard Hope, of Railway Gazette
magazine believed the problem may have been caused by inexperienced
workers.
"It may be that they were taken off during
an inspection and somebody forgot to put them back on. Or somebody didn't
tighten them up properly and they were shaken loose."
Inspections
Railtrack has admitted that it carried out
work on that section of track, including the points, last year.
But it said the work was to do with "gauge
corner cracking" which it and other experts agreed was not an issue
in the Potters Bar accident.
|
Points inspections
|
1 May: Tests
and inspections
9 May: Visual
inspection
All inspections by
fully-qualified staff
Tests to recognised
standards
Source: Jarvis
|
Jarvis said the track had been subject to two
recent checks - tests and inspections on 1 May, and visual checks on
9 May.
"In both cases, these tests and inspections
were carried out by full-time Jarvis employees. No sub-contracted personnel
were involved."
It added that tests were carried out in accordance
to standards recognised by the Institute of Railway Signalling Engineers.
However, a Jarvis employee contacted BBC News
24 to say workers were under pressure to "cut corners".
He claimed the track was checked less frequently
than it was under British Rail, and said safety was being sacrificed
for profit.
Experts are mystified
as to why the nuts were missing
|
The rail union RMT said a worker had alerted management
three weeks ago to the fact that bolts were missing at the points, and
that the track in that area was generally in a poor state - but had received
no response.
Union leader Bob Crow said rust and a lack
of maintenance probably caused the accident: "I think the vibrations
of the train allowed the nuts to come off the bolts."
Mr Crow and others said there was a problem
with the complex structure of responsibility for maintenance work.
Railtrack bears responsibility for the work,
but it farms it out to companies such as Jarvis, who in turn subcontract
out work to hundreds of different firms.
All report to the HSE, but there are concerns
than lines of responsibility have become blurred.
Mr Crow said safety standards were not high
enough because there were not enough track inspectors, and too many
casual workers.
Labour's George Stevenson MP, of the Transport
Select Committee, said there was a simple answer.
"The government must now take the next logical
step, and take into public control all the railway infrastructure."